Day 10 – May 20, 2011:

The decking and crossbeams were treated and set out to dry while a splice for one of the cables was completed.  More rock slinging going on to try to work on the approach to the left tower. First set of crossbeams began with our fearless leaders starting us out in teams of four. This day we learned that even light sprinkling of rain will shock people when using a generator.  Our progress on the crossbeams and decking turned out to be slow at first but by the time the second team went up we were setting about 4 crossbeams each hour.